ANALISIS PENJADWALAN PROYEK DENGAN METODE PDM DAN PERT PADA PEMBANGUNAN RUAS JALAN SIMPANG ARMED – RUMAH GERAT KECAMATAN BIRU-BIRU KABUPATEN DELI SERDANG (STUDI KASUS)

dc.contributor.authorTelaumbanua, Titus Asli Sabarhati
dc.date.accessioned2024-11-12
dc.date.available2024-11-12
dc.date.issued2023
dc.identifier.uri https://jurnal.uisu.ac.id/index.php/JTSIP/article/view/8814
dc.description.abstract The construction of the Armed- Gerat House Intersection Road, Biru-Biru District, Deli Serdang Regency, applies scheduling using the S Curve method, in which the linkages between critical activities cannot be known so that the activities that are prioritized and cannot be carried out late in the project cannot be visible and there is no efficient time to be able to complete the project. Therefore the PDM and PERT methods are applied, so that project scheduling planning can determine the interrelationships between activities, determine which activities need to be considered (critical activities), determine the probability of completion of all project work. The purpose of this research is to find out how the PDM and PERT methods are applied in the scheduling of road construction projects that initially used the S-Curve method in their scheduling so as to produce a time schedule with the right work duration and have a high probability of success. From the results of the planner's calculations on the Intersection Road Development project. Armed - Gerat House, Biru-Biru District, Deli Serdang Regency, using the PDM method used by researchers, the overall duration of project activities is 128 working days, the same as the duration of the planner's S Curve with a critical path, namely activities A-D-E-E3-E1-E2-D1-G -A1. Whereas using the PERT method, the results show that the probability of successful completion of the project with a duration of 128 days is only 70%, with the PERT method, an efficient time for project completion is obtained, namely 132 days which has a probability of 99.63% with the critical path of activities A-D-E-E3-G- A1. Keywords: PDM and PERT method scheduling en_US
dc.language.isoenen_US
dc.publisherUniversitas Harapan Medanen_US
dc.subjectPENJADWALAN PROYEK en_US
dc.titleANALISIS PENJADWALAN PROYEK DENGAN METODE PDM DAN PERT PADA PEMBANGUNAN RUAS JALAN SIMPANG ARMED – RUMAH GERAT KECAMATAN BIRU-BIRU KABUPATEN DELI SERDANG (STUDI KASUS)en_US
dc.typeSkripsien_US


File In This Item

No Thumbnail
Name ad5cdd1762a2cd58eb19fcbf6086b838Titus Asli SabarHati Telaumbanua.docx
Size 676999 Mb
Format application/vnd.openxmlformats-officedocument.wordprocessingml.document
Description peer_review
Peer Review

This item appears in the following Collection(s)

Skripsi [1458]

Show Simple Item Record