PERANCANGAN ULANG TATA LETAK RUANG PRODUKSI BATU BATA UNTUK MENGURANGI JARAK MATERIAL HANDLING DENGAN METODE SYTEMATIC LAYOUT PLANNING (SLP) (STUDI KASUS DI PT. SURYA JAYA AGUNG) DESA SEI BULUH, KEC. PERBAUNGAN, KAB. SERDANG BEDAGAI

dc.contributor.authorChairani, Winni
dc.date.accessioned2025-07-17
dc.date.available2025-07-17
dc.date.issued2024
dc.identifier.uri JRSI:JurnalRekayasaSistemIndustri,Universityof PuteraBatam(ISSN:2477.2089;E-ISSN:2621.1262).
dc.description.abstract Redesigning the Layout of Production Area of The Brick Factory to Reduce Material Handling Distance Using Systematic Layout Planning (SLP) Method (Case Study at PT. Surya Jaya Agung, Sei Buluh Village, Perbaungan District, Serdang Bedagai Regency). PT. Surya Jaya Agung is a processing industry that produces both solid red bricks and concrete bricks with a capacity of 15,000 pieces per day or approximately 35 tons per day. To meet customer demand for the company's products, the company aims for high productivity with an effective and efficient work system. The current condition shows that the production area used for production activities is 2,570 m², while the actual material handling distance is 160 meters. To address this issue, research was conducted to obtain a factory layout that would reduce the distance between departments, thereby reducing material handling and optimizing the production area using the Systematic Layout Planning (SLP) method. Based on the Systematic Layout Planning (SLP) method, two alternatives were obtained for the redesign of the factory layout. Among the two alternatives, Alternative I is the best solution, where the proposed redesign will save the production area from 2,570 m² to 2,306.1 m², a difference of 263.9 m². This Alternative I will also save the material handling distance from 160 meters to 43.65 meters, a difference of 116.35 meters. Keywords: Solid Red Brick, Concrete Brick, Factory Layout, Systematic Layout Planning (SLP) en_US
dc.language.isoenen_US
dc.publisherUniversitas Harapan Medanen_US
dc.subjectTATA LETAK RUANG PRODUKSI BATU BATA en_US
dc.titlePERANCANGAN ULANG TATA LETAK RUANG PRODUKSI BATU BATA UNTUK MENGURANGI JARAK MATERIAL HANDLING DENGAN METODE SYTEMATIC LAYOUT PLANNING (SLP) (STUDI KASUS DI PT. SURYA JAYA AGUNG) DESA SEI BULUH, KEC. PERBAUNGAN, KAB. SERDANG BEDAGAIen_US
dc.typeSkripsien_US


File In This Item

No Thumbnail
Name 68e125510d8c92d69353a50ddb0a65a9Jurnal winni.docx
Size 523636 Mb
Format application/vnd.openxmlformats-officedocument.wordprocessingml.document
Description fulltext
Fulltext
No Thumbnail
Name 68e125510d8c92d69353a50ddb0a65a9WINNI CHAIRANI.docx
Size 144673 Mb
Format application/vnd.openxmlformats-officedocument.wordprocessingml.document
Description peer_review
Peer Review

This item appears in the following Collection(s)

Skripsi [1508]

Show Simple Item Record